The past month has been extremely productive, and we are excited to share the latest progress:
- Concrete pouring for the pool is complete, along with the installation of the water filtration and lighting systems.
- Gypsum plastering of all residential corridors has been finished.
- Installation of metal structures for composite aluminum panels on the building facade is complete.
- Automatic control systems for the elevator zone have been installed.
- The ventilation system is 95% installed.
- Granite tiling in the corridors is 50% completed.
- Installation of point electrical cables in residential areas is ongoing.
- Installation of composite aluminum panels on the roof is in progress.
- Balcony railings installation is ongoing.
- Stair railing installation has begun.
- Installation of aluminum panels along the building facade has started.
Stay tuned for more updates on the construction progress!